1. Pipe Laying

Layout Patterns

Snake (Meander)

Simple, low material waste. Higher pressure drop on long loops. Best for small zones.

Spiral

Even heat distribution. Self-balancing. Preferred for heat pump systems.

Double Spiral

Two spirals fed from centre. Best for large areas >20m² per loop.

Key Rules

  • Max loop length: 100m (16mm), 120m (17mm), 80m (12mm)
  • Min bend radius: 5×OD (80mm for 16mm, 85mm for 17mm)
  • Clip spacing: 300mm (PEX), 600–800mm (Alu-PEX), 200mm on bends
  • Expansion joints: every 30m² or 6m max dimension — pipe conduit required
  • Doorways: conduit sleeve, pipe not in screed across threshold
  • Manifold tails: minimum 300mm free pipe for connection

Fixings by Floor Type

FloorFixing MethodClip/Rail
Screed on insulationPipe clips + grip rail60mm clips @ 300mm / grip rail
Timber joistsSpreader plates + staplesAlu plates, staple to joists
Floating overlayRouted insulation boardsPre-grooved boards
Batten systemClips to battensPipe clips @ 300mm

2. Manifold Connection

Pipe Preparation

  1. Cut pipe square with pipe cutters (not hacksaw)
  2. Remove burrs internally and externally
  3. Check pipe ovality — reject if >0.5mm
  4. Mark insertion depth on pipe (fitting depth + 2mm)

Fitting Types

  • Eurokonus (3/4″): Compression, reusable, 16×2mm & 17×2mm
  • Soft-Seal (1″): O-ring seal, push-fit, 16×2mm only
  • Press-Fit (16/20mm): Permanent, requires press tool, Alu-PEX compatible

Labelling

Label BOTH ends of every loop: zone number, room name, loop length. Use cable ties with printed tags or permanent marker on heat-shrink.

3. Pressure Testing

MANDATORY before screed pour. Document with photos + signed test certificate.

Procedure

  1. Close all manifold flow/return valves
  2. Connect test pump to manifold fill/drain valve
  3. Pressurise to 1.5× design pressure (min 6 bar, max 10 bar)
  4. Hold for 30 minutes — no visible pressure drop
  5. Inspect every joint, fitting, manifold connection
  6. Record: date, time, pressure, duration, tester name, witness
  7. Photo every manifold, every joint cluster
  8. Leave system pressurised until screed poured (min 24hr)

Test Certificate Must Include

  • Project address & plot number
  • System type (screed/timber/overlay)
  • Pipe type & size
  • Test pressure & duration
  • Pass/Fail + any remedial actions
  • Installer signature + company stamp

4. Commissioning

Flushing & Filling

  1. Remove all actuator heads (if fitted)
  2. Open all flow & return valves
  3. Connect mains to fill valve, hose from drain valve to waste
  4. Flush each loop individually — min 2 minutes clear water
  5. Fill system slowly — vent air at manifold air vents
  6. Check pressure: 1.5–2.0 bar cold

Air Removal

Run pump at max speed. Open air vents until water flows steadily. Repeat daily for 3 days. Automatic air vents: check weekly.

5. Balancing

Flow Meter Method (Combimix/Standard with flow meters)

  1. Calculate target flow per loop: Q = (Heat load × 0.86) / ΔT (litres/hour)
  2. Set all flow meters to calculated values
  3. Run system 30 mins, verify return temps within 2°C of design
  4. Fine-tune: reduce flow on hot loops, increase on cold
  5. Record final flow meter readings

Temperature Method (No flow meters)

  1. Run system to steady state (1+ hours)
  2. Measure flow & return temp at manifold per loop
  3. Target ΔT: 5–10°C (heat pump), 10–15°C (boiler)
  4. Adjust return valves: close on low ΔT, open on high ΔT
  5. Iterate until all loops within 1–2°C of target

6. Startup & Screed Drying

Gradual Warm-Up Protocol (BS EN 1264 / CIBSE)

DayFlow TempDurationNotes
1–320–25°C24hr/dayGentle drying, no thermal shock
4–725–30°C24hr/dayIncrease 2°C/day
8–1430–35°C24hr/dayMax 35°C for first 28 days
15–2835–45°CPer designNormal operation after day 28

Critical Rules

  • Do NOT exceed 35°C flow for first 28 days (screed curing)
  • Do NOT force-dry with high temps — causes cracking
  • Keep rooms ventilated — moisture must escape
  • Record daily flow/return temps for warranty

Client Handover Checklist

  • As-built drawings (pipe layouts, manifold schedules)
  • Commissioning & balancing records
  • Pressure test certificate
  • Thermostat programming guide
  • Maintenance schedule (annual: air vents, inhibitor check, pump)
  • Warranty registration